Question 9:

You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks? 

Answer options:

A. Resource Management Plan
B. Risk Management Plan
C. Stakeholder management strategy
D. Communications Management Plan