ExamQuestions.com

Register
Login
Certified in Risk and Information Systems Control Exam Questions

Isaca

Certified in Risk and Information Systems Control

97 / 500

Question 97:

You are the project manager of a SGT project. You have been actively communicating and working with the project stakeholders. One of the outputs of the "manage stakeholder expectations" process can actually create new risk events for your project. Which output of the manage stakeholder expectations process can create risks? 

Answer options:

A. Project management plan updates
B. An organizational process asset updates
C. Change requests
D. Project document updates