Which of the following is an acceptable method for handling positive project risk?
Answer options:
A. Exploit
B. Avoid
C. Mitigate
D. Transfer
Answer correct:
A
Exploit is a method for handling positive project risk. Incorrect Answers: B, C, D: These are all responses which is used for negative risks, and not the positive risk.