Question 150:
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
Answer options:
A. Risk register B. Work Performance Information C. Project management plan D. Change requests