Question 180:
You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of $350,000. When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
Answer options:
A. The risk exposure of the event is $350,000. B. The risk exposure of the event is $500,000. C. The risk exposure of the event is $850,000. D. The risk exposure of the event is $245,000.