Question 200:

You are the project manager of GHT project. You want to perform post-project review of your project. What is the BEST time to perform post-project review by you and your project development team to access the effectiveness of the project? 

Answer options:

A. Project is completed and the system has been in production for a sufficient time period
B. During the project
C. Immediately after the completion of the project
D. Project is about to complete