Question 255:

Assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes which of the following processes? 

Answer options:

A. Qualitative Risk Analysis
B. Plan Risk Management
C. Identify Risks
D. Quantitative Risk Analysis