Question 340:

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via. email every week. You have agreed and send reports every Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project? 

Answer options:

A. Configuration management
B. Communications management
C. Perform integrated change control process
D. Project change control process