Question 101:
During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering committee`s FIRST action?
Answer options:
A. Require a revised business case. B. Approve the budget request. C. Provide appropriate training. D. Refer back to the project sponsor for resolution.