Question 273:

Which of the following is the BEST method to confirm whether a pilot project was successful? 

Answer options:

A. Evaluate whether the pilot project achieved planned schedule and cost.
B. Review the metrics recorded in the IT balanced scorecard.
C. Assess the results of the pilot project against the expected performance outcomes.
D. Determine whether the pilot aligns with the as-is enterprise architecture (EA).