Question 67:
Which of the following metrics represents the maximum duration of time allowable for a restoration process to take place i.e. the duration of time within which the business process must be restored after the disaster to avoid any unacceptable or undesired consequences?
Answer options:
A.RPO (Recovery Point Objective) B.RTO (Recovery Time Objective) C.RMO (Recovery Mode Objective) D.Retention period