ExamQuestions.com

Register
Login
Microsoft Dynamics 365 Supply Chain Management, Manufacturing (MB-320) Exam Questions

Microsoft

Microsoft Dynamics 365 Supply Chain Management, Manufacturing (MB-320)

2 / 112

Question 2:

DRAG DROP - A skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the same sub assembly item and resource sanding process. You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce. You must make a permanent change to the number of units the resource can produce for all future orders. You need to adjust the process quantity on the route operation. Which three actions should you perform in sequence? To answer, move the appropriate actions form the list of actions to the answer area and arrange them in the correct order. Select and Place: 
image