Question 94:
You are the production scheduler at a manufacturing company. The company is not using advanced warehousing. You have firmed a planned production order from master planning. The order is ready to be processed. You now need to process the order in production control. What should you do first?
Answer options:
A. Report the order as finished B. Estimate the order C. Schedule the order D. Start the order