Question 16:
The close cycle covers seven days and consists of three days of pre-close preparation tasks, one day to close the books, and then three days of reviewing, analyzing and reporting. To define a Task Manager task template to monitor all seven days, which day range should you define?
Answer options:
A. Day " 3 to Day 3 B. Day " 2 to Day 4 C. Day 1 to Day 7 D. Day " 3 to Day 4