Question 111:

Which is a purpose of the Risk theme? 

Answer options:

A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problems that have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks