Question 124:

Which is a purpose of the Managing a Stage Boundary process? 

Answer options:

A. Provide the Project Board with sufficient information for approving the next stage
B. Approve the next Stage Plan
C. Review and close any risks and issues identified during the previous stage
D. Control the link between the Project Manager and the Team Manager(s)