Question 139:

Identify the missing words in the following sentence. When proposed changes [ ? ], the change authority must refer the decision back to the project board. 

Answer options:

A. are below the agreed change budget
B. are objected to by team members
C. are rejected by the change authority
D. exceed the agreed change budget