Question 142:

What action is taken as part of the `controlling a stage` process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products 

Answer options:

A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4