Question 178:
According to PRINCE2, why might there be more than one business case for a project?
Answer options:
A. There may be more than one management stage in the project B. The project may be in a commercial environment with a number of suppliers C. There may be more than one work package being delivered in the project D. The project may be in a programme environment