Question 207:

Which is a purpose of the `initiating a project` process? 

Answer options:

A. To produce a stage plan for each stage of a multi-stage project
B. To enable the project board to decide whether it is worthwhile to initiate a project
C. To provide a fixed point at which acceptance for the project product is confirmed
D. To enable an organization to understand the work needed to deliver the project`s products