Question 213:

Which statements about quality assurance and project assurance are CORRECT? 1. They are both independent of the project manager 2. They are both the responsibility of the project board 3. They are both independent from the project management team 4. They both assure that applicable standards are being used 

Answer options:

A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4