Question 219:

Identify the missing words in the following sentence. The `managing a stage boundary` process should be executed [ ? ] a management stage. 

Answer options:

A. when a stage plan has been prepared for
B. at the beginning of
C. when all the delivery steps have been completed within
D. at, or close to the end of,