Question 37:
Which is NOT a purpose of the Initiating a Project process?
Answer options:
A. Enable a Project Board decision about the commitment of resources to a project B. Enable an organization to understand the work that needs to be done to deliver a project`s products before a project is approved C. Establish solid foundations for a project D. Enable the Project Board to decide whether it is worthwhile to initiate a project