Question 41:
Which is a purpose of the Managing Product Delivery process?
Answer options:
A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package B. Provide a controlled link between the Project Manager and the Team Manager(s) C. Enable the Project Board to request updates to the current Team Plan D. Establish solid foundations for the project