Question 48:
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Answer options:
A. Create a separate Project Board to manage the supplier elements of the project B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project`s stages. C. Create user and supplier groups D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board