Question 68:

Which is assumed to be a supplier`s responsibility in the PRINCE2 customer/supplier environment? 

Answer options:

A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project