Question 115:

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project`s threats and opportunities. 

Answer options:

A. change budget
B. project budget
C. project`s cost tolerance
D. project`s risk tolerance