ExamQuestions.com

Register
Login
PRINCE2 Foundation Exam Questions

PRINCE2

PRINCE2 Foundation

180 / 230

Question 180:

Why is the `initiating a project` process used? 

Answer options:

A. To decide which project approach is suitable for the project
B. To fully understand how the project objectives will be achieved before committing significant resources
C. To produce the required work packages
D. To enable corporate or programme management to give authorization to deliver a project