Question 126:

M1ich statement is an appropriate entry for the outline Business Case heading within the Project Brief? 

Answer options:

A. 10 year service contract should be agreed with the selected service provider.
B. External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits.
C. The project will run for two years and the benefits will be realized over 1a years.
D. The project should be split into four management stages.