Question 134:
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of 250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?
Answer options: