Question 164:

The project is part of a program to develop more training courses that respond to new legislation. The project manager has requested that project support be made available from the program. As a result, the executive has confirmed that this will be carried out by the program office. Is this appropriate, and why? 

Answer options:

A. Yes, because the program office should provide support to projects, if requested.
B. Yes, because the project support role is not optional and must be provided.
C. No, because the project manager should take on project support responsibilities.
D. No, because program and project team structures need to be separate.