Question 172:

The Sales Director would like to add a new company logo to the `marketing material`. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of £500 has not been used. Which option describes how this change should be funded? 

Answer options:

A. £400 of the stage 2 cost tolerance and the £500 change budget should be used.
B. £900 needed for the change should be taken from the stage 2 cost tolerance.
C. £900 of additional funding will need to be requested to pay for the change.
D. £400 will need to be requested in addition to the £500 change budget.