Question 181:
MANAGING PRODUCT DELIVERY - Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the `classroom-based training material` discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in response?
Answer options: