Question 184:
The project is approaching the end of stage 3, and stage 4 is being planned as part of the `managing a stage boundary` process. Which action should the project manager carry out as part of the `update the project plan` activity?
Answer options:
A. Include the actual time and cost of the work to prepare the `marketing materials` in the project plan. B. Ensure that the team manager for the work package `delivered pilot courses` is included as a resource. C. Update the project`s business case to show any new key risks that have been identified. D. Include the tolerances for the work package `delivered pilot courses` in the project plan.