Question 188:
The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the `capability to provide health and safety training`. Is this appropriate, and why?
Answer options:
A. Yes, because a plan should be created to measure the number of courses carried out after project closure. B. Yes, because a separate closure stage plan should be created during stage 4. C. No, because closure activities should have been planned at the end of stage 3. D. No, because user acceptance of the project`s products should have taken place throughout the project.