Question 4:

Which of the following statements is FALSE regarding the Continued Business Justification? 

Answer options:

A. The justification for the project must remain the same throughout the project
B. The justification for the project should remain valid
C. The justification for the project may change
D. If the project is no longer justified it should be stopped