Scenario - Additional Information - 
image
Further information on some resources who could be involved in the project: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the Outcome Account Manager: consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project. She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious Director of Finance Division: approach is adopted in all operational and project activities across the Ministry of Food Hygiene. Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the Hardware Manager: needs of his colleagues working in software. Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Payroll Manager: Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry`s business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards. Which 2 alternative actions apply to the proposed Senior User for this project? 

Answer options:

A. Retain because he provides the outsourcing resources required to support the project.
B. Replace with `Director of Research and Development` because she deals with both the Information Technology and the Facilities Divisions and can make sure her division`s needs are specified.
C. Remove because he has no authority to commit user resources.
D. Add `Hardware Manager` because he provides computer hardware to all business functions and will be impacted by the outcome.
E. Retain because he will be providing support to the Information Technology and Facilities teams during the project.