Question 150:

Which of the following management products ARE updated as part of Managing a stage boundary? 1. Business Case 2. Benefits Review Plan 3. Configuration Item Records 4. Project Brief 

Answer options:

A. 1, 2, 3
B. 1, 3, 4
C. 1, 2, 4
D. 2, 3, 4