Question 170:
During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages. Is this appropriate for a risk register, and why?
Answer options:
A. Yes, because the project registers should be tailored to meet the needs of the organization. B. Yes, because risks are often identified as a result of issues being raised. C. No, because an integrated project register should include the quality register as well. D. No, because assumptions and dependencies are sources of risk.