PRINCE2 Practitioner Exam Questions

PRINCE2

PRINCE2 Practitioner

175 / 200

Question 175:

The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the `e-learning course` incrementally. The project manager has asked the program manager how often the highlight reports are required, and what format the reports should be presented in. Is this an appropriate approach to controlling progress, and why? 

Answer options:

A. Yes, because the approach should support the delivery approach selected by the program.
B. Yes, because the project event-driven controls need to align to program controls.
C. No, because the program team should review project progress using peer reviews.
D. No, because the progress controls should be documented in the project initiation documentation.