113 / 130

Question 113:

Which activity takes place within the Managing a Stage Boundary process? 

Answer options:

A. Produce Highlight Reports
B. Take corrective action within the limits of a stage`s tolerance
C. Produce an Exception Plan
D. Authorize a Stage Plan for the next stage