Question 122:

Which is NOT undertaken during the Initiating a Project process? 

Answer options:

A. Review why the project is needed
B. Identify if the project is sufficiently aligned with corporate objectives
C. Show how the outcome is to be achieved
D. Appoint an Executive and Project Manager