Question 16:

Which is an objective of the Starting up a Project process? 

Answer options:

A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled