Question 2:

Which of the following statements about lines of authority and reporting are true? 1.The Project Manager has day-to-day control for a management stage within the limits laid, 2.If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board. 

Answer options:

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true