Question 34:
Which statement is FALSE?
Answer options:
A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit B. A project`s output is any of the project`s specialist products C. A project benefit is only realized after the project has closed D. A project outcome is the result of the change derived from using the project`s outputs