ExamQuestions.com

Register
Login
PRINCE2 Re-Registration Exam Questions

PRINCE2

PRINCE2 Re-Registration

48 / 130

Question 48:

Which is a purpose of the Controlling a Stage process? 

Answer options:

A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan