Question 63:
Which of the following is NOT a purpose of the Closing a Project process?
Answer options:
A. Plan the activities required to close a project B. Enable a comparison of the original objectives of a project against what was actually achieved C. Enable premature closure if the Project Board request that a project should no longer continue D. Provide a fixed point at which acceptance for the project product is confirmed