Question 9:
Which of the following statements about the Project Initiation Documentation are true? 1.The Project Initiation Documentation is used to ensure that a sound basis exists. 2.The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,
Answer options:
A. Only 1 is true B. Only 2 is true C. Both 1 and 2 are true D. Neither 1 or 2 are true