Question 65:

Which of the following statements about the Closing a Project process are true? 1.The Closing a Project process provides a fixed point for the receipt of completed Work 2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage. 

Answer options:

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true