CompTIA Project+ Exam Questions

CompTIA

CompTIA Project+

152 / 350

Question 152:

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs? 

Answer options:

A. Pareto chart
B. Fishbone diagram
C. Process diagram
D. Run chart