Question 152:
A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
Answer options:
A. Pareto chart B. Fishbone diagram C. Process diagram D. Run chart